75.2% Completion Achieved on Gas Roundabout–Bilad Sur Road Dualisation Project


Date Published: 23 April 2026

Road Transport

The Gas Roundabout–Bilad Sur Road Dualisation Project has reached 75.2% completion, at a cost exceeding OMR 6 million, as part of efforts to enhance road safety and improve connectivity between governorates.


The Ministry of Transport, Communications and Information Technology continues implementing the remaining works on the project, which links the Quriyat–Sur Road with Sultan Turki bin Said Road (formerly Al Sharqiyah Road), and completes the dualisation of the Quriyat–Sur Road from Gas Roundabout to Bilad Sur Roundabout in South Al Sharqiyah Governorate.

Share Now: |

The first section of the project, spanning 11.4 kilometres, has been completed, including street lighting and metal safety barriers. Work is currently under way on the second section, extending 3.5 kilometres, which includes converting the existing single carriageway into a dual carriageway, constructing service roads and several box culverts, in addition to lighting works, protective measures, and the installation of traffic and directional signs.


The project also includes the construction of a new roundabout near Sur College, as well as the rehabilitation and upgrading of several side access points, enhancing economic activity and meeting the needs of residents in the area.


The project is expected to improve traffic flow for road users travelling from Muscat Governorate to the Wilayat of Sur and South Al Sharqiyah Governorate, while also supporting economic and social development, enhancing infrastructure efficiency, and strengthening safe and effective connectivity in line with urban growth.